PIUnit (PIBatch) Configuration Help Options · View
Big2
#1 Posted : Tuesday, March 09, 2010 11:18:27 PM
Rank: Newbie
Groups: Member

Joined: 3/9/2010
Posts: 9
Location: Baton Rouge, LA
I've been working on getting a PIUnit configured for one of our reactors. We currently do not have any defined.

I have been using PI SMT. I have a configuration module named on the server and its module appears under the PIUnit I created.

The Active Point is a Performance Equation that goes to 1 during a reaction and 0 when out of reaction. This performance equation is functioning and the PIUnitBatch Behavior is set to Pulse (I have tried Step as well). No Unit Batch ID Point or Procedure Name Point are entered, but I do have a Product Name Point entered. These are listed as optional in the Configuration help files.

I have no PISubBatches currently defined.

In PIBatches I have only entered in a Product Name Point and Search Time. The rest were listed as optional in the configuration help files.

The Active Point has gone through several 1 to 0 and 0 to 1 cycles and no PIBatches or PIUnitBatches have been created from what I can find. If I go into the Batch Database, then it will let me manually create a PIBatch and I can manually create a PIUnitBatch associated with my PIUnit. The PIBatch and PIUnitBatch I manually defined I can view in quicksearch, processbook, and the batch database.

Any help at all?

Thanks in Advance!
Sponsor  
 
Michael
#2 Posted : Wednesday, March 10, 2010 4:28:26 PM
Rank: Advanced Member
Groups: Member

Joined: 12/3/2009
Posts: 71
Location: Germany/Pennsylvania
Hi Big,

First of all: in your case Pulse is correct. The configuration you made should work.

Stupid question: Is your Batch system running? It's also called PI Batch Generator Interface or PIBaGen.

Michael


Big2
#3 Posted : Wednesday, March 10, 2010 4:39:15 PM
Rank: Newbie
Groups: Member

Joined: 3/9/2010
Posts: 9
Location: Baton Rouge, LA
Michael wrote:
Hi Big,

First of all: in your case Pulse is correct. The configuration you made should work.

Stupid question: Is your Batch system running? It's also called PI Batch Generator Interface or PIBaGen.

Michael




That is a stupid question...

And it was the correct question, PI Batch Generator was not running d'oh!

It was started and it went back and generated the missed PIUnitBatchs. It did not generate any PIBatches, and honestly, I don't understand the difference between PIBatches and PIUnitBatches other than PIUnitBatch is suppose to be for one piece of equipment.

The strange thing is I updated my SMT to 3.2.4 and I cannot see the PI Services, but IT still has 3.2.3 and they can see the PI Services. What I get for updating my software. I'm going to send the error log to OSI about it.
Michael
#4 Posted : Wednesday, March 10, 2010 5:45:34 PM
Rank: Advanced Member
Groups: Member

Joined: 12/3/2009
Posts: 71
Location: Germany/Pennsylvania
You named it: The main difference between PIBatch and PIUnitbatch is that a PIUnitBatch is linked to a location / equipment and a PIBatch is independent.

This has a consequence: You can have only ONE PIUnitbatch for ONE dedicated PIUnit at ONE time.

You have to analyze your business processes to decide which parts are PIBatches, PISubbatches PIUnitbatches and how the material transfer (PITransferrecord) is organized. Refer to the ANSI S88 standard.

If you like, describe your business process here and we can try to sort it out.

Michael

EDIT: Keep in mind that OSI is replacing PIBatch with AF based EventFrames!!!
Big2
#5 Posted : Wednesday, March 10, 2010 9:32:08 PM
Rank: Newbie
Groups: Member

Joined: 3/9/2010
Posts: 9
Location: Baton Rouge, LA
So, Is this correct?

A PIBatch will be used to track one "Batch" through several Units? i.e. a PIBatch would have several PIUnitBatches to track a batch of beer through a PIUnit for the Mash Tun, and then the PIUnit for the Lauter Tun, and then the PIUnit for the Fermenter, etc.?

Then each PIUnit would have its own PIUnitBatch and each of those PIUnitBatches would be linked to the main PIBatch.

Then, for example, the PIUnit for the Mash Tun would have PISubUnitBatches to represent different steps on that unit such a PISubUnit for charging with grain, a PISubUnit for adding Strike Water, a PISubUnit for the Enzyme rest, etc.?




Michael
#6 Posted : Thursday, March 11, 2010 4:57:47 AM
Rank: Advanced Member
Groups: Member

Joined: 12/3/2009
Posts: 71
Location: Germany/Pennsylvania
Perfect explanation!

Just some remarks:

There is no PISubUnitBatch, it is simply called PISubBatch.
The different steps (filling, adding sth, processing, emptying, etc) at this equipment are the PISubBatches of this PIUnitBatch (mash tun). There were no PISubUnits because everything is done using the same equipment.
As a hint, you can add PISubBatches to a PISubBatch, so hierarchy is allowed.

Michael (had a Pilsner Urquell)
Big2
#7 Posted : Thursday, March 11, 2010 3:32:17 PM
Rank: Newbie
Groups: Member

Joined: 3/9/2010
Posts: 9
Location: Baton Rouge, LA
Thanks for the help! I read all kinds of documents on PIBatch and PIBatchview and PI Batch Generator and didn't fully grasp the difference until now.

And I only wish I made beer professionally Sad
Users browsing this topic
Guest
Forum Jump  
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.